英语翻译成型机头安装程序视机头大小而定,最多四人安装,用时10-15分钟一、 准备工作1.准备两条载重超过机头重量2倍的软体吊装带,平铺于地面上,将机头缓慢滚动至吊装带上,两端挂
来源:学生作业帮助网 编辑:作业帮 时间:2024/11/17 11:25:42
英语翻译成型机头安装程序视机头大小而定,最多四人安装,用时10-15分钟一、 准备工作1.准备两条载重超过机头重量2倍的软体吊装带,平铺于地面上,将机头缓慢滚动至吊装带上,两端挂
英语翻译
成型机头安装程序
视机头大小而定,最多四人安装,用时10-15分钟
一、 准备工作
1.准备两条载重超过机头重量2倍的软体吊装带,平铺于地面上,将机头缓慢滚动至吊装带上,两端挂在吊车勾上准备起吊。严禁将吊装带从机头内穿过,以免起吊时将机头牵拉变形
2.清洗机头主轴孔和成型机主轴上的灰尘,上少许润滑油,使安装顺畅。
二、安装
1 将连接套装在成型机主轴上
2吊起机头,使轴孔与主轴对接,旋转主轴,使主轴上的键条与机头上的键槽在一条水平线上
3借助吊车之力,一人操作吊车,两人平推机头,使之与主轴上的连接套相连接。如推入费劲,可操作吊车,使成型机主轴与机头平行,严禁用重物撞击机头,以免机头变形,影响机头使用寿命
4确认装机后,放下吊车,紧固机头,装机完成
5卸机头按反向操作
英语翻译成型机头安装程序视机头大小而定,最多四人安装,用时10-15分钟一、 准备工作1.准备两条载重超过机头重量2倍的软体吊装带,平铺于地面上,将机头缓慢滚动至吊装带上,两端挂
Molding Head Setup
Depending on head size of up to four people to install,with 10-15 minutes when
First,the preparatory work
1.Ready to load more than 2 head 2 times the weight of hoisting with the software,tiled on the ground,will head slowly scroll to the hoisting belt,hung on the crane hook at both ends of the preparations for lifting.Lifting strictly prohibited within the zone from the nose through to avoid lifting the nose when the stretch deformation
2.Cleaning the nose spindle hole and the dust on the machine spindle,on a little oil to make installation smooth.
2,the installation
1 will be connected to suit the machine spindle
2 lifting the nose,so that shaft hole and spindle docking,rotating spindle,so that a key on the spindle head of the keyway with the machine in a level line
With the power of three cranes,one to operate cranes,two flat push the nose to make the connection with the spindle sleeve connected.Such as the push into the strenuous,operable crane,so that machine spindle nose parallel,non-impact head with heavy objects to prevent head deformation,affecting the nose life
4 confirmed installed after the cable car down,fastening the nose,installed complete
Unloading head 5 by the reverse operation of 虽说是抄的.但查了机子,确实是这样...汗...
Molding Head Setup
Depending on head size of up to four people to install, with 10-15 minutes when
First, the preparatory work
1. Ready to load more than 2 head 2 times the weight of hoist...
全部展开
Molding Head Setup
Depending on head size of up to four people to install, with 10-15 minutes when
First, the preparatory work
1. Ready to load more than 2 head 2 times the weight of hoisting with the software, tiled on the ground, will head slowly scroll to the hoisting belt, hung on the crane hook at both ends of the preparations for lifting. Lifting strictly prohibited within the zone from the nose through to avoid lifting the nose when the stretch deformation
2. Cleaning the nose spindle hole and the dust on the machine spindle, on a little oil to make installation smooth.
2, the installation
1 will be connected to suit the machine spindle
2 lifting the nose, so that shaft hole and spindle docking, rotating spindle, so that a key on the spindle head of the keyway with the machine in a level line
With the power of three cranes, one to operate cranes, two flat push the nose to make the connection with the spindle sleeve connected. Such as the push into the strenuous, operable crane, so that machine spindle nose parallel, non-impact head with heavy objects to prevent head deformation, affecting the nose life
4 confirmed installed after the cable car down, fastening the nose, installed complete
Unloading head 5 by the reverse operation of 记得采纳
收起
Molding Head Setup
Depending on head size of up to four people to install, with 10-15 minutes when
First, the preparatory work
1. Ready to load more than 2 head 2 times the weight of hoist...
全部展开
Molding Head Setup
Depending on head size of up to four people to install, with 10-15 minutes when
First, the preparatory work
1. Ready to load more than 2 head 2 times the weight of hoisting with the software, tiled on the ground, will head slowly scroll to the hoisting belt, hung on the crane hook at both ends of the preparations for lifting. Lifting strictly prohibited within the zone from the nose through to avoid lifting the nose when the stretch deformation
2. Cleaning the nose spindle hole and the dust on the machine spindle, on a little oil to make installation smooth.
2, the installation
1 will be connected to suit the machine spindle
2 lifting the nose, so that shaft hole and spindle docking, rotating spindle, so that a key on the spindle head of the keyway with the machine in a level line
With the power of three cranes, one to operate cranes, two flat push the nose to make the connection with the spindle sleeve connected. Such as the push into the strenuous, operable crane, so that machine spindle nose parallel, non-impact head with heavy objects to prevent head deformation, affecting the nose life
4 confirmed installed after the cable car down, fastening the nose, installed complete
Unloading head 5 by the reverse operation of
收起
……哪些文字?